At 9:18 of September 3, along with joyful firecrackers, the16000kw WHG project collocating 10000t/d production line of China United Cement Xuzhou Corporation contracted by Conch Kawasaki Company (in EPC method) successfully connected in grid and generated electricity.
China United Cement Corporation (CUCC) is one of important company of the China National building Materials Group Corporation (CNBM).The CUCC’s capitalization subsidiary, China United Cement Xuzhou Corporation is the group's important cement enterprise. In order to further alleviate the factory’s power supply intense condition, reduce the production cost, raise company's operation level, China United Cement Xuzhou Corporation finally signed the EPC contract with Anhui Conch Kawasaki Engineering Company Limited for the 16000KW WHG project collocating the company’s 10000t/d clinker production line after the multi-wheel negotiations and the exchange in August 2007.
The project smooth connecting in grid will bring the good economic and social efficiency for the CUCC Xuzhou Corporation, become another economic growth point, and greatly enhance its market competition. At present, this WHG system is optimizing the operation process, actual generation electricity capacity already stabilized in 13000KW.

The WHG units successfully connected in grid

Clean and neat steamer workshop

PH horizontal boiler at kiln inlet