Time:2010-03-10 00:00
See:
At 20:35,on Mar 8, 2010, Guiding Conch Panjiang Company's 110KV transformer substation start test run loaded with power, and at 21:08, the transformer substation smoothly fulfilled all the tests, with all the parameters staying normal, equipments stably running and successfully one-off receiving power.

Accepting thecommmand of receiving power
All parameters were normal and equipments smoothly operating