|     conch group    |   

The Third Set of WHG Unit of Chizhou Conch Succeeded in Grid

Time:2008-08-01 00:00

See:

The third set of 18000kW project of Chizhou Conch succeeded in grid on July 31 2008.

The third set of WHG project relied on 2*4500t/d clinker production lines, collocated 4 WHG boiler and 1 rated power approximately 18000kW steamer units, the power rate designed 40kwh each ton clinker.

Since this project's succeeded in operation, which smoothly realized connection the grid plan, became the company’s new economic growth.

The 18000kW WHG unit operated with-load