Recently, Anqing power-supply Company arranged for the people in planning department, marketing department and other related departments to inspect the grid connection of second WHG in Zongyang Conch.
The Inspection team deeply comes into the site to know the WHG process in detail. They gave high evaluation to the second generator unit construction quality, progress and the management, and made relevant requirements to the grid connection. At the summary meeting, the two parties discussed and studied the problems appeared in the inspection process and reached a consensus.

Two parties are exchanging

Inspection team is seriously checking the commissioning

Watching WHG data commissioning