Chizhou Conch 11600kW WHG system succeeded in grid connection

Time:2007-11-02 00:00

See:

At 3:08am on November 1, the second 11600KW WHG system of Chizhou Conch succeeded in grid connection and operating.

This project is the second WHG system of Chizhou Conch after the first 17000kw WHG system of Chizhou Conch operated successfully

The project relied on the 8000t/d clinker production line, matching 3 boilers and one set mixed steam type condensing turbine and generator designed for the 11600 kW generating power.

This project’s operation realized that the second WHG system of Chizhou Conch succeeded in grid connection on time, will become a new economic growth spot for Chizhou Conch.