Time:2008-10-14 00:00
See:
Xing'an Conch WHG Unit Collocating Phase I Clinker Production Line succeeded in grid on October 12, 2008.
Xing'an Conch WHG project started in December 28, 2007. It spent more nine months to put into operation.The project planned to construct WHG Unit collocating 2×4500t/d clinker production line, build four boilers and a set of steamer generator unit, total installing capacity is 18MW. This successful connecting in grid for Phase I clinker production line, included two boilers and generators, which gained in the experiences for the Phase II project, based a solid foundation on developing circulation economy, advanced energy conservation and emission reduction.