  Recently, the foundation grouting work of gasification furnance and sewage pit, and the purchasement work of main equipments for Pingliang conch CKK project have been completed. The construction of this project was started in september of last year, and expects to be put into operation in september of this year.

  This project plans to build one CKK line with capacity of 300 ton per day, and consists of one solid waste pre-treatment and furnance incineration building, 2 sets of ground weigher, tie-in work between gasification furnance gas duct and calciner, road construction in the south side of plant and relevant utilities and auxiliary facilities.etc.. This project is the first CKK project in the west area of China.(translator:Wangshan)

Source: China Gansu website