Time:2010-02-11 00:00
See:
At 8:00, on Feb.9,2010, Dazhou Conch Project I 5000t/d clinker production line successfully passed performance index examination on reaching the production and standard for 72 hours. It was to speed up conch cement clinker goods to be placed on the market that the project was smoothly put into operation and reached the production and standard , so then it would strongly support reconstruction after Sichuan earthquake.

The CCR personnels were seriously operating

Quality under just-in-time monitor