Since carrying out deeply studying and practicing the scientific concept of development activities in March this year, Ningguo Cement Plant 5000t/d clinker production line has made continued success,following the continuous high output in April,May and June: production of high quality clinker exceeded this month's plan by 5.85%, while coal consumption declined by three percentage points less than target , and kiln operation rate came up to 100% for two consecutive months, and created best levels in history.

Ningguo Cement Plant's 5000t/d cement production line and overlooking the railway line
The rotary kiln of 5000t/d production line under the greenwood tree
The pre-heater and integrated control house against the blue sky