Xing'an Conch second 4000T/D clinker production lines successfully was put into operation on April 2, produced the clinker 1008 tons in the same day.
The company put into the busy trial production immediately after the 4000T/D production line ignited one 29 March. The company formulated the detailed and escort plan for feeding materials to rotary kiln, established escorted the leadership team and experts team, reasonablly arranged personnel, focused on quality control, the process operation, the equipment escorted and so on.
All staff participating in the task are on duty in 24 hours,devoted themselves to the commissioning work, promptly solved the occurred difficulties and problems during the trial production, assured of the trial production busily and orderly.
At present, Xing’an Conch’s staff morale surges upward, each work of trial production developed busily and orderly.