Shuangfeng Conch Phase II 5000T/D Clinker Producion Line was Successfully Put into Operation

Time:2009-04-01 00:00

See:

Shuangfeng Conch realized to put into operation on 31 march and produced the first batch of qualified clinker in the same day since its phase II 5000T/D clinker producion line successfully ignited on 26 March.

The company mobilised all strength to arrange trial production since the line ignited on 26 March ,The raw materials mill smoothly realized the first full load movement on March 28 and produced the material more than 8000 tons, which assured that kiln system running.The commissioning experts stayed on the site each day, combed and handled the possible problem during the trial production,guaranteed the production line running stability.