Guangyuan Conch held a ceremony on completion and commissioning of Project I and commencement of Project II's main construction

Time:2010-03-21 00:00

See:

On Mar. 20, 2010, the ceremony on completion and commissioning of Guangyuan Conch Project I and commencement of Project II's main construction was warmly held. Concerning this project, the completion and commissioning of Project I and commencement of Project II's main construction with a milestone significance on industry development progress of Guangyuan City, was an important measure making a benign interaction between enterprise and local development, and was dynamic practice on advancing resource transformation strategy.

The ceremony site

Announcing completion of Guangyuan Conch Project I and main construction commencement of Project II

The key leaders attending the ceremony cut the ribbon for Guangyuan Conch Project I

 

The key leaders attending the ceremony laid a foundation for main work of Project II

 

Visiting central control room